Azerbaijan Expands Grid to Connect More Renewable Energy Sources

World News Agencies • By AZERTAC • 23 November, 2026

Jerusalem, 23 November, 2026 (TPS-IL) -- Baku (AZERTA) – The construction of one of the largest and highest-voltage transmission lines in the Azerbaijani energy system has begun.

AzerEnergy told AZERTAC that within the second phase of the “Expansion of Renewable Energy Sources in Azerbaijan – AZURE” project, construction of a 235-kilometer-long 500-kilovolt high-voltage transmission line from Mingachevir to Navahi has begun.

This 500-kilovolt line, built at the highest voltage class in the country, is of strategic importance in terms of expanding the transmission capabilities of the energy system and safely and reliably integrating newly created renewable energy sources into a single energy system. At the same time, the project will ensure the formation of a 500-kilovolt circular energy scheme covering the western, central and eastern regions of Azerbaijan, and the transmission of energy over long distances with less loss. At the same time, it will expand the possibilities of regulating the frequency and power balance in the energy system and flexible management of energy flows.

Significant infrastructure work has already been carried out.

The construction of one of the largest substations in the country – the new 500/300 kilovolt “Navahi Green Energy Junction” – has been completed using the internal resources of “AzerEnergy” and partly from the state budget. Also, the construction of 500 kilovolt transmission lines from Navahi to Absheron, with a total length of more than 245 kilometers, and 330 kilovolt transmission lines to the “Bilasuvar” and “Banka” solar power plants has been completed. As a result, the necessary infrastructure has been created for the connection of both solar power plants to the country’s unified energy system.

In the second phase of the AZURE project, it is planned to equip the “Navahi Green Energy Hub” with transformers and reactors, and to build new transmission lines of 500 kilovolts in the direction of Mingachevir from Navahi, and 330 kilovolts in the directions of Alat, Absheron and Gobu. The construction of the 500 kilovolt Mingachevir-Navahi line has already begun. The construction of three transmission lines of 330 kilovolts will start soon.